A team of four highly trained roofers took on the works during winter months, completing the job within the desired time frame, with just eight weeks from start to completion.

With an hour spent every day wiping away condensation from the roof due to cold weather, the team worked fastidiously to identify where leakages were occurring. A scraper machine was used to remove outdated stone chippings that had been placed on top of bituminous roof felt, before installing a primer to the stripped back roof, followed by a base coat, reinforcing and then topcoat and the addition of a quartz walkway to provide safe maintenance access.

All of the work undertaken has a guarantee of twenty years and feedback from the client was very positive.