The company was appointed to reroof two areas at Hudson Road Primary School.

A six-strong team worked on the project during the 2019 summer holiday.

Objectives:

  • The main roof had come to the end of its life and required a Bauder total roof overlay VCL, 120mm insulation, underlay and cap sheet. This provided high tensile strength, elongation and tear resistance
  • The roof has a 20 year guarantee
  • Within a smaller roof, tapered insulation was used to eliminate ponding which the original structure did not cater for
  • Replacement cladding was undertaken to perimeter

Customer Feedback

The project was undertaken and completed within the budget and timescale. Quality checks took place on a daily basis as well as regular supplier quality checks to maintain compliance.