IMG_6350 (2)

Calor Gas, Port Clarence, Middlesbrough

Appointed by Lambert, Smith and Hampton to deliver the works.

The site was heavily flooded through high tides having a damaging effect on the sites offices.

Objectives

  • To strip out a disused storage area which had a steel framed mezzanine floor construction
  • The area to be transformed into a habitable office space homing a large office area, two meeting rooms, disabled wc, wash rooms, kitchen and sales counter
  • A metal framed extension to form the sales entrance cladded in Cedar Wood
  • Air conditioning units, new lighting, decorations and windows all to be installed
  • Upon completion of the works, a project that saw the site team move into a new environment with a vase amount of office space
  • Phase two of the works will include demolishing the old office areas and refurbishing the security office, first aid room and visitor receptions area

  Customer Feedback:

All stakeholders were delighted with the progress and the professionalism of the site teams working in a restricted environment.